                     Corpus Christi LNG 3rd project is 56% complete, as Cheniere pursues expansions 
                    2024/05/03 
                    Cheniere Energy has said that its Corpus Christi LNG 3rd stage project (CCL Stage 3) is 55.9% complete (engineering 89.3%, procurement 74.8%, subcontract work 75.4% and construction 16.5%). 
                    The complete article is available to subscribers after login. 
                     
                    